The project was to replace 16,000 feet of steam distribution piping serving 20 barracks and dining facilities with kitchens while they were in full-time use. All had to be done while not removing any buildings ... CLICK HERE TO READ THE ENTIRE PROJECT OVERVIEW >>
• Direct-buried piping, secondary containment, cathodic protection, welds x-rayed
• 6,000 feet of temporary above ground by-passes
• Only 4 partial day shutdowns
• 15,000 man-hours
• No injuries, no accidents, no incidents
• Completed ahead of schedule