GLASS MANUFACTURER
Expansion of Facility
NEW COMPRESSOR PLANT
Foundations and Underground Work
CASTING PLANT
Installation of New Processing Pit
WOOD TREATMENT FACILITY
Expansion and Upgrade of Facilities

The project was to expand a glass manufacturing facility and install the corresponding above ground and below ground conveyance systems. The below

ground conveyance system required a large amount of excavation and the construction of 250 feet of 12-foot deep tunnel. It all had to be done

without a single shutdown... CLICK HERE TO READ THE ENTIRE PROJECT OVERVIEW >>

• 250 feet of 12-foot deep tunnel


• Below ground and above ground conveyors


• 4,500 cubic yards of excavation inside an operational manufacturing plant


• Shoring span of 50 feet to support roof


• 5,000+ man hours, 87 days, no plant shutdowns


• No lost time injuries